9 October 2017

For NCC, Linotol has shed the floor to E.ON’s new recycling facility at Högby Torp in Upplands-Bro municipality. The acting including laying concrete took over 18 hours in line. Two pumps were required to cast around 60 m3/h to the 1 meter thick plate. E.ON’s investment is one step in developing the Högby Torp to the future recycling facility.

Images

More news

Concrete Constructor of the Year 2017!

Concrete Constructor of the Year 2017!

28 November 2017

Congratulations to this year’s Concrete Constructor of the Year, Dorotea Sigurdadottir. Linotol...

Car park Palissaden in Kungälv

Car park Palissaden in Kungälv

27 October 2017

Bergman & Höök builds a prefabricated multi-storey car park with 3 200 sqm piled baseplate....

New design floor at the entertainment venue Conventum

New design floor at the entertainment venue Conventum

23 October 2017

Linotol has shed a durable design floor for the client Örebroporten at Conventum Arena in central...